TABLE OF CONTENTS
Introduction
Environmental
Monitoring and Audit Progress
Breaches
of Action and Limit Levels
Construction
Noise
Complaint
Log
Notification
of Summons and Successful Prosecutions
Reporting
Changes
Future
Key Issues
Purpose
of the report
Structure
of the report
Background
Project
Organization
Summary
of Construction Works Undertaken During Reporting Month
Construction
Programme
Status
of Environmental Licences, Notifications and Permits
Monitoring
Requirements
Monitoring
Location
Monitoring
Equipment
Monitoring
Parameters, Frequency and Duration
Monitoring
Methodology and QA/QC Procedures
Maintenance
and Calibration
Results
and Observations
Event
and Action Plan
4 ENVIRONMENTAL
SITE INSPECTION
Site
Audits
Implementation
Status of Environmental Mitigation Measures
Solid
and Liquid Waste Management Status
5 ENVIRONMENTAL
NON-CONFORMANCE
Summary
of Exceedances
Summary
of Environmental Non-Compliance
Summary
of Environmental Complaint
Summary
of Environmental Summon and Successful Prosecution
Key
Issues in the Coming Two Months
Monitoring
Schedule for the Next Month
Construction
Programme for the Next Month
7 CONCLUSIONS AND
RECOMMENDATIONS
Conclusions
Recommendations
LIST OF TABLES
Table I Summary
Table for Monitoring Activities in the Reporting Month
Table II Summary
Table for Events Recorded in the Reporting Month
Table III Summary Table for Site Activities in the
coming Two Months
Table 2.1 Work
Contracts undertaken in the Reporting Month
Table 2.2 Key
Contacts of the Project
Table 2.3 Summary
Table for Major Site Activities in the Reporting Month
Table 2.4 Status
of Environmental Licenses, Notifications and Permits
Table 3.1 Location for Noise Monitoring Stations
Table 3.2 Noise Monitoring Equipment
Table 3.3 Noise
Monitoring Parameters, Duration and Frequency
Table 3.4 Summary
Table of Noise Monitoring Results during the Reporting Month
Table 3.5 Observation
at Noise Monitoring Stations
Table 4.1 Observations
and Recommendations of Site Audit
Table 4.2 Photographic
Records of Measures
Table 6.1 Summary
Table for Site Activities in the coming Two Months
LIST OF DRAWINGS
Drawing no.
60335576/C1/C00/1031A-1051D Site
Layout Plan (Contract No. ND/2019/01)
Drawing no.
60335576/C6/C00/1041 Site
Layout Plan (Contract No. ND/2019/06)
LIST OF FIGURES
Figure 1 Location
of Noise Monitoring Station (Contract No. ND/2019/06)
Figure 2 Location
of Noise Monitoring Station (Contract No. ND/2019/01)
LIST OF APPENDICES
Appendix A Construction
Programme
Appendix B Action
and Limit Levels
Appendix C Copies of Calibration Certificates
Appendix D Environmental Monitoring
Schedules
Appendix E Noise Monitoring Results and Graphical
Presentation
Appendix H Summary
of Exceedance
Appendix J Environmental
Mitigation Implementation Schedule (EMIS)